3.6 Costs Requiring Prior Approval

Introduction

2 C.F.R. § 200.407 sets out costs that require prior, written approval. A list of the most common of these costs for DOJ grantees is also included below. Award recipients must obtain prior written approval for any of these costs. Recipients must also receive prior written approval for costs that contain special limitations (such as expenditure ceilings).