3.11 Indirect Costs

Approval of Indirect Cost Rates for Subrecipients

Direct recipients of Federal funding are responsible for approving indirect cost rates for their subrecipients. Such rates must be consistent with the requirements of 2 C.F.R. § 200. The Federal awarding agency will not approve indirect cost rates beyond the direct recipient level; however, subrecipients who are also direct recipients of Federal awards may already have a Federally approved indirect cost rate. If a subrecipient has negotiated an indirect cost rate with the Federal government, then that rate applies.